Port of Þorlákshöfn requests bids for preparation for a new Suðurvararbryggja quay by building a new breakwater south of existing breakwater and lengthening of the Suðurvarargarður breakwater by 250 m.
Key volume figures:
Quarry blasting filling materials 250.000 m3
Utilization of armor stone quarry 195.000 m3
Replace existing armour stones 58.000 m3
Dredging to -9,0 m 10.000 m3
Land reclamation 13.000 m3
Demolish of Suðurvarabryggja quay 200 m
The project is divided into six phases which has their own delivery dates:
Phase 1: Building of a new berm breakwater west of existence breakwater.
Deliver date is 15th of Sptember 2022.
Phase 2: Construction of a road on the harbour side of Suðurvarargarður.
Deliver date is 1st of Oktober 2022.
Phase 3: Dredging behind Suðurvarabryggja quay to -5,0 m
Deliver date is 1st of May 2023.
Phase 4: Remove of Suðurvarabryggja quay which is made of concrete casions.
Deliver date is 15th of June 2023.
Phase 5: Remove the cofferdam on the breakwater end
Deliver date is 15th of August 2023.
Phase 6: Lengthen of the Suðurvaragarður berm breakwater of 250 m.
Deliver date is 15th of November 2023.